Pavement Maintenance

 

Pavement Maintenance Program:  2019

      Streets Covered:

              Marygate

              Norfolk

              Lindford

              Lisaview

              Welshire

              Debbington

              Buchanan

              Millard

              Dwight

              Parkside

2019 Pavement Maintenance     

Click here for full screen view

 

       Contractor:  Chagrin Valley Paving

                             17290 Munn Rd

                             Chagrin Falls, OH 44023

       Contract Price:  $739,034

       Start Date:  April 29, 2019

       Completion Date:  TDB

       Project Milestones:  Milling of the top 2" of asphalt: COMPLETE

                                      Installation of Leveling Course: COMPLETE

                                      Replacement of curb as deemed necessary COMPLETE

                                       Adjustment of manholes and catch basins as required: COMPLETE

                                       Installation of new pedestrian ramps: COMPLETE

                                       Installation of 2" of new asphalt:

Special Notes:  

Access to driveways will be maintained during the project unless there is a need for concrete repair work.

Traffic through the project will be maintained by the contractor, but there will be no detours.

During the project, the contractor will be applying a liquid binding layer to promote adhesion of the new asphalt layers. Please avoid driving on this layer unless absolutely necessary.  This material will stick to your tires and potentially track onto your driveway.  If this occurs, please be patient, the product will fade over the course of the rest of the year.

6-19-19 Update

Paving Project: Activities update:

Curb replacement:  Completed

Casting adjustments:  Completed

Installation of Ped. Ramps:  Completed

Paving is underway and sould be completed by end of day